The Blackburn Point Bridge reaches its centennial this year, and its future is tentatively going before the Sarasota County Commission in December. The engineering reports, petitions and public hearings mostly turn on one feature. The bridge is 16 feet wide and carries a single lane. Sarasota County's project team names that lane as a core reason the structure is "functionally obsolete." The Sarasota Alliance for Historic Preservation describes the same lane as what keeps traffic slow on the north end of the island. Every option on the county's list amounts to an answer about that lane.
The Structure in Question
The bridge carries Blackburn Point Road over the Gulf Intracoastal Waterway and connects Osprey and Casey Key. It was built between 1925 and 1926 and is listed on both the National Register of Historic Places and Sarasota County's local register. The Sarasota Alliance for Historic Preservation describes it as a Warren pony truss swing structure that originally opened by hand crank. The Alliance also calls it the last surviving bridge from the young county's first round of public works during the 1920s land boom, as the Sarasota News Leader reported.
The county presented a June 2026 deck at its third public meeting, which was posted on the Blackburn Point Bridge Project site. It says the bridge is one of eight highway swing spans still in service in Florida, and its repair log has grown denser over time. After work in 1997, 2006, 2009, 2012, 2016 and 2019, the county logged repairs every year from 2020 through 2025.
Drivers who cross often already wait out the bridge's rhythm. Since Aug. 12, 2024, the span has opened for boats on the hour, at 20 minutes past and at 40 minutes past between 7 a.m. and 7 p.m. That schedule does not apply on weekends and holidays. The county's FAQ puts a typical opening at roughly 5 to 10 minutes, based on the bridge logs.
What the County Measures
The county's case rests on standards. The project site lists:
- A 16-foot roadway carrying one lane
- No sidewalks, shoulders or bike lanes
- Railings that do not meet current standards
- Exposure to corrosion over the water
Navigation is the second part of the case. The open span gives boats 51 feet of horizontal clearance and 9.3 feet of vertical clearance. The U.S. Coast Guard's guide clearances are 90 feet and 21 feet.
The June presentation rates the bridge at "Current Condition State = 3 – Serious," a rating that indicates serious effects on primary structural components. County spokesperson Emily Blaine said the study weighs "public safety, mobility, emergency access, quality of life for nearby residents and users, environmental considerations, and the bridge's history, character and surrounding area." Your Observer reported her statement on Nov. 2.
What the Preservationists Measure
Dave Baber reads the same structure differently. He is immediate past president of the Alliance and spent 13 years as director of the Sarasota County Department of Historical Resources, where he helped place the bridge on the county register. "They drive full cement mixers over it all the time, so it's not unsafe," he told Your Observer. "And it acts as a traffic calming because it's one lane wide."
Baber says "functionally obsolete" is a transportation term for a bridge that falls short of current highway standards, and that the bridge itself works. "It's functional. They said it's in fair condition," he told the paper. He proposes guardrails attached to the decking to improve pedestrian safety on the historic structure. He also told the paper that the last substantial work on the bridge was in 1995, when the span stayed swung open for several weeks. In 1999 he was part of a group that studied moving the bridge somewhere else, and they found nowhere to take it.
The Alliance asked Michigan-based Bach Ornamental & Structural Steel, a historic bridge restoration firm, to review the county's records. Nels Raynor, the company's president, concluded that "rehabilitation is the fiscally conservative option, by a wide margin." The company reached that conclusion from documents, photographs, video and cost estimates rather than an on-site inspection.
The Options, and How Width Drives Cost
The county is studying a no-build option that keeps the single-lane bridge with the repairs needed to stay in service. It is also studying replacement with a new swing span or a single-leaf bascule drawbridge, in single-lane or two-lane form. The June presentation compares the replacement designs by relative cost ratios rather than dollar totals:
| Replacement design | Bascule | Swing |
|---|---|---|
| Single lane, one sidewalk | 1.2 | 1.6 |
| Two lanes, one sidewalk | 1.3 | 1.7 |
| Two lanes, two sidewalks | 1.5 | 1.8 |
Each added lane or sidewalk raises the ratio, and every swing design costs more than the bascule of the same width. A new swing span would keep the bridge's familiar motion, and the table shows it is the most expensive way to do that.
The county also prices the bridge it already has. The presentation estimates the present value of continued maintenance and repair, followed by eventual replacement, at about $31 million. The project FAQ says keeping the existing bridge would cost more than $20 million over 20 years. As of the Sept. 23 budget hearing, the county had appropriated $3.7 million for the "Blackburn Point Road Movable Bridge," and no new money was programmed through fiscal year 2031. The county's Capital Improvement Program sheet lists Hardesty & Hanover as design consultant on a $2,088,184 design contract and says construction is not funded in the five-year plan.
Whatever the Commission chooses, the bridge north Casey Key crosses will not change soon. The county's FAQ says the Commission makes the final decision after the project team's recommendation. It expects final design to take roughly a year and finish in the third quarter of 2027, and construction money has not been identified.
How the Island Has Weighed In
The Alliance put the bridge on its 2025 Six to Save list of endangered historic places. Since then the effort has included door-to-door outreach on the northern part of Casey Key, a Facebook page and, by late September, nearly 2,000 signatures on a Change.org petition plus handwritten petitions from community meetings. About 100 people attended the county's third public meeting on June 11 at the Church of the Holy Spirit in Osprey, and Baber said most of them favored preservation.
The bridge also took over a budget night. At the Commission's final hearing on the 2026-27 budget on Sept. 23, all but two of the public speakers addressed the bridge, the Sarasota News Leader reported. Curtis Albee Vannah of Nokomis, whose great-uncle Dr. Albee came to the area in 1920, told commissioners the bridge has "passed safety inspections" and is "a natural speed barrier on Blackburn Point Road."
In an Oct. 13 statement, the county said no final decision had been made and that the topic was tentatively scheduled for Commission discussion in December 2026. The Commission's December regular meetings fall on Dec. 15 and 16, according to the County Commission page.
The Road on the Other Side Is Already Changing
The road beyond the bridge is part of the same question. Laura Roush of Casey Key Road told commissioners in September that the narrow road has no bike lane and no sidewalks, and she asked for traffic studies before any change that might bring more cars onto it. Part of Casey Key's road network is being rebuilt now.
The county's North Casey Key project sheet, updated November 2026, shows the north roadway temporarily shifted west while permanent reconstruction proceeds. Work at the south end is nearing completion, and the county schedules completion for spring 2027. The construction contract with de Moya CHC Joint Venture LP totals $44,590,755.48. Your Observer described the stretch as 0.53 miles long.
Utility crews are also on the island this week. Sarasota County lists daytime FPL stub-pole work, 9 a.m. to 4 p.m., through Nov. 13 in these locations:
- Casey Cove Drive, from Casey Key Road to Key Way
- South Casey Key Road, from Albee Road west to the end
- Casey Key Road, from Gulf Winds Way to Sea Grape Point Road
Both ends of the island are under construction this fall. The northern entrance is the one still waiting for a decision, and the timed openings on the hour, at 20 past and at 40 past still set the pace for anyone crossing on a weekday.
For more about life on the island in quieter months, see our look at Casey Key in summer and the Casey Key neighborhood guide.
At Suncoast Luxury Team, we follow north Casey Key one crossing at a time, from the bridge schedule to the road work south of it. If you own on the island and want a clear read on what these projects mean for your property, reach out to schedule a private conversation or request a valuation.